| Sheppard AFB Elementary School |
|
{Sheppard} |
Location: 301 Anderson (SAFB)
Architect: Bundy, Young, Sims & Potter
Project Architect/Engineer: TBD
Anticipated Finish Date: 8/2010
Status: Site work foundation pad prep | |
|
Project |
Method |
Contractor |
% Complete |
Start Date |
Original Cost |
Final Cost |
| Replace 10 heat., vent., & AC systems |
CSP |
TBD |
100% |
6/1/2008 |
$239,800 |
$312,991 |
| Local education facility upgrades |
GC |
TBD |
0% |
6/1/2010 |
$81,750 |
|
| OT/PT and adaptive PE space |
GC |
TBD |
2% |
6/1/2010 |
$0 |
|
| Content mastery/resource room |
GC |
TBD |
2% |
6/1/2010 |
$0 |
|
| Tutoring space and storage |
GC |
TBD |
2% |
6/1/2010 |
$0 |
|
| Other building improvements |
GC |
TBD |
2% |
6/1/2010 |
$163,500 |
|
| Replace electrical switchgear |
CSP |
TBD |
100% |
6/1/2009 |
$119,900 |
$47,380 |
| Exterior window replacements |
GC |
TBD |
0% |
6/1/2010 |
$109,000 |
|
| Teaching gym |
GC |
TBD |
10% |
11/1/2009 |
$599,500 |
|
| Replace fire alarm panel |
WFISD |
TBD |
100% |
6/1/2009 |
$16,350 |
$6,332 |
| Bathroom renovations |
WFISD |
TBD |
50% |
6/1/2010 |
$54,500 |
|
| Exterior door replacements |
WFISD |
TBD |
100% |
3/1/2010 |
$87,200 |
$22,722 |
| Location Totals |
|
|
|
|
$1,471,500 |
| |
|